Foundation
Lot preparation completed,
footing is completed,
foundation is set.
|

Frame Complete
All of the home’s interior
and exterior walls are set,
and the roof framing is complete.
|

Windows & Shingles
The Builder has completed
the installation of windows,
shingles, and exterior sheathing.
|
Ready for Drywall
Electrical, HVAC and plumbing systems are installed. Municipal inspections are completed.
|
Drywall Completed
Brick or stone exterior
is begun. Wall and ceiling
textures are completed
to finish Stage 5.
|
Wood Trim and
Door Installation
This stage is completed
after interior doors are set,
and moldings have been installed.
|
Kitchen & Bath
Cabinet Countertops
Kitchen cabinets are set
and countertops installed
to reach Stage Seven.
Interior painting is also done.
|
Carpet & Flooring Installed
At Stage Eight, your home’s
plumbing and electrical fixtures
will be set. The Builder will also
install the flooring in your home.
|

Builder Acceptance
The Area Construction
Manager and your Personal
Builder perform a quality
inspection on your home
at this stage.
|